Working for Oelrich Construction, SanPik installed approximately 13,000ft of force main, water main and reclaim water main PVC and ductile iron pipe ranging from 4” to 24”. The installation also included stormwater RCP pipe, manholes of approximately 1,300ft, sanitary sewer manholes and approximately 1,500ft of PVC piping. Throughout the project SanPik also removed and abandoned all existing utilities and replaced them with the new utilities included in the scope of work. The project value was $2.5 Million.