PROJECTS
Our clients are our top priority, and getting the job done quick and precise is our major concern.
Priding ourselves with our high level of competitiveness and the will to go above and beyond to exceed your expectation will blow you away. Take a look at some of our past projects to see how Sanpik Inc. gets things done in ways other contractors can’t.

Water Main
Water pipelines are the lifeblood of our communities
MLK Roadway & Pedestrian Improvements
- Type: Water Main
The work generally consisted of the complete reconstruction of MLK Blvd, widening the sidewalks to 8-feet on both sides, curb and gutter, new water main and water services, gravity sewer system and sewer laterals, relocating power poles to backside of sidewalk, landscaping and irrigation, and street lights.
MLK Roadway & Pedestrian Improvements
Lake Marion
- Type: Water Main
SanPik Incorporated was subcontracted by Garney Construction to complete the installation of all of the yard piping for a treatment plant which included force main, portable water main, drain lines, reclaimed water main, sanitary sewer pipes, manholes, 2ea lift stations and other mechanical piping all ranging in sizes from 2” through 36”.
Lake Marion
Bluford Ave Phase 2
- Type: Water Main
Working for Oelrich Construction, SanPik installed approximately 13,000ft of force main, water main and reclaim water main PVC and ductile iron pipe ranging from 4” to 24”. The installation also included stormwater RCP pipe, manholes of approximately 1,300ft, sanitary sewer manholes and approximately 1,500ft of PVC piping. Throughout the project SanPik also removed and abandoned all existing utilities and replaced them with the new utilities included in the scope of work.
Bluford Ave Phase 2
SR46 Utility Relocations
- Type: Water Main
Installation of approximately 27,000ft of force main, water main and reclaim water main. Pipe sizes range from 6” up to 24” in size. We also installed approximately 1,500ft of 10” gravity sewer and manholes. After the installation of the above-mentioned pipe, 24,000ft of the original pipe was removed.
SR46 Utility Relocations
Reclaimed Water Main Interconnect
- Type: Water Main
SanPik was responsible for the installation of 2000ft of 16” reclaimed water main, gate valves, fittings and de-watering.
Reclaimed Water Main Interconnect
South Water Treatment Plant Re-Pipe
- Type: Water Main
This project consisted of 12″ through 20″ DIP pipe for treatment plant inclusive of an Above Ground Assembly with Mag Meter & Static Mixer. We completed the construction of this project ahead of the original time frame and helped the City of Ocoee save big money that was being—literally—expelled daily through leaking, old pipes. Since then the water treatment plant has been operating under much less stress. SanPik was thanked by the Ocoee local government for a job well done and done quickly due to it being a time-sensitive project.
South Water Treatment Plant Re-Pipe

Lift Stations
Wastewater liftstations challenge gravity's pull by moving wasterwater from lower to higher elevations
City of Maitland Lift Station #1 Relocation
- Type: Lift Station
SanPik was awarded this job by the City of Maitland in 2021. This job consisted of the installation of 6,000lf of PVC sewer pipe sizes ranging from 8″ to 24″. 3,320lf of 14″ HDPE Force Main. Complete road, sidewalk and landscape restoration. Also included demolition of existing lift station and the installation of a new submersible triplex lift station.
City of Maitland Lift Station #1 Relocation
Lift Station 33 Osceola Parkway Gravity Sewer Rehabilitation
- Type: Lift Station
SanPik Inc. was awarded this project in 2023 by the TOHO Water to open cut and replace gravity sewer mains, laterals, and manholes. The project also consisted of the rehabilitation of gravity sewer mains and laterals by use of Cured-In-Place-Pipe (CIPP) lining, and manholes by sealing and coating.
Lift Station 33 Osceola Parkway Gravity Sewer Rehabilitation
Lift Station 18 Scott Blvd Gravity Sewer Rehabilitation
- Type: Lift Station
TOHO Water Authority awarded this project to SanPik Inc. This project consisted of replacing gravitysewer mains, laterals, and rehabilitate gravity sewer mains and laterals by Cured-In-Place-Pipe (CIPP) lining, and rehabilitate manholes by sealing and coating, within the Scott Blvd area.
Lift Station 18 Scott Blvd Gravity Sewer Rehabilitation
Mt. Dora Master Lift Station #53
- Type: Lift Station
This project included the installation of a brand-new lift station for the City of Mt. Dora. The lift station included two 30ft deep wet wells, 85HP pumps, associated mechanical piping, 400kw generator and site work. The offsite work included approximately 16,000 ft of 2” HDPE conduit via directional drill, 1,000 ft of PVC WM and RWM, 500ft of 12” gravity sewer and three jack & bores underneath an active railroad.
Mt. Dora Master Lift Station #53
Cypress West WRF
- Type: Lift Station
Working for Wharton Smith Inc., SanPik completed the installation of approximately 4,000ft of Force Main, Gravity Sewer, Stormwater Drainage and a 24” Injection Line. Despite the site being heavily congested, SanPik was able to plan efficiently with numerous subcontractors and maintain a tight schedule to complete the scope of work on time.
Cypress West WRF
Consumer Court Liftstation No. 62
- Type: Lift Station
We were called on to install a new sanitary 10ft diameter lift station along with two manholes and the associated gravity and force main piping in a tight dead-end corner of Consumer Ct., in the City of Ocoee. We were able to self-preform the necessary de-watering for the 30ft excavation. A 30ft by 20ft by 18ft slide rail trench box was utilized to maintain a safe work environment. We delivered the project on time, on budget, and with no change orders.
Consumer Court Liftstation No. 62

Gravity Sewer and Force Main
Sanitary sewer system installation and maintenance are critical to public and environmental safety
Lift Station 1B Gravity Sewer Rehabilitation
- Type: Sewer
TOHO Water Authority awarded this project to SanPik Inc. This project consisted of replacing gravity sewer mains, laterals, and rehabilitate gravity sewer mains and laterals by Cured-In-Place-Pipe (CIPP) lining, and rehabilitate manholes by sealing and coating, within the LS-1B Hermosillo basin service area.
Lift Station 1B Gravity Sewer Rehabilitation
Sandhill WRF Linework
- Type: Sewer
SanPik was the subcontractor for this project under Wharton Smith who was the general contractor. SanPik was contracted to install all the linework utilities on the TOHO Wastewater Treatment plant. SanPik installed approximately 3,500LF of 16” and 24” DIP.
Sandhill WRF Linework
Ponce De Leon Septic To Sewer Project
- Type: Sewer
This project consists of construction of approximately 1,200 LF of 8” PVC gravity sewer and sanitary manholes, 1,300 LF of force main as well as a new lift station including wet well, pumps, valves, piping and electrical. Selective demolition, minor stormwater revisions and restoration items are included as well.
Ponce De Leon Septic To Sewer Project
DB Lee WRF Gravity Interceptor
- Type: Sewer
SanPik Inc was awarded this project by the City of Melbourne. The project consisted of approximately 2,000’ of 36” Gravity Sewer, 160’ of gravity sewer installed by jack & bore with a 54” steel casing. The installation of 11 manholes ranging from 12ft deep up to 20ft deep and the removal of 800’ of 8” gravity sewer pipe. The entire project required dewatering via well points. There was also sidewalk, road, and landscape restoration as part of this project.
DB Lee WRF Gravity Interceptor
Aloma Avenue And Dean Road Gravity Main Reconnection
- Type: Sewer
SanPik was awarded this project as part of a continuing contract with South Seminole and North Orange County Wastewater Transmission Authority (SSNOCWTA). This project consisted of the installation of 1,500’ of HDPE ranging from 4” to 16”. We also installed approximately 60ft of 42” PVC FM, 220ft of 36” PVC FM along with 42” and 36” Plug Valves. On this site, we also installed a 42’ knife gate valve in the center of a busy intersection overnight. Concrete, asphalt, and road restoration, maintenance of traffic, dewatering and bypass pumping were also a significant aspect of this project.
Aloma Avenue And Dean Road Gravity Main Reconnection
Gravity Wastewater System Improvements
- Type: Sewer
Included gravity sewer utilities repaired and rehabilitated in 9 sub-areas throughout Orange County. Installation consisted of approximately 2,300ft of gravity sewer, replacement of 16 manholes and relocation of 39 sewer laterals. Most of the work required dewatering, bypass pumping and were 14ft to 22ft deep.
Gravity Wastewater System Improvements
South Bermuda
- Type: Sewer
For this project, SanPik Incorporated was subcontracted by Wharton Smith Inc. and was responsible for cutting and removing approximately 25′ of damaged 42” ductile iron pipe. The ductile iron pipe was replaced with 42”C905 DR21 PVC. The work also included by-passing the existing sewer as well as dewatering via a well point system.
South Bermuda
Sewerage System Pipeline Installation
- Type: Sewer
SanPik was contracted by Wharton Smith to install approximately 3,000 ft of 12″ HDPE pipe and approximately 3,000 ft of 16″ HDPE pipe using the traditional open-cut method along the Esterly Tibbets Highway on Grand Cayman for the Cayman Water Authority. The fusion work was completed using both a McElroy Cart 412 fusion machine and a McElroy Tracstar 618 fusion machine.
Sewerage System Pipeline Installation

Storm Drainage
Storm drainage systems don't just keep residents of cities safe from flooding
Virginia Monroe Stormwater System
- Type: Storm Drainage
Construction of two storm water pump stations with force mains, two storm water ponds and additional conveyance enhancements such as inlets and storm water pipes. Installation of 1,900’ of RCP in various sizes ranging from 12” up to 36”. Construction of water services along with new water mains, road restoration along with concrete curb, sidewalk, and driveways replacements.
Virginia Monroe Stormwater System
Lake Davis to Lake Greenwood
- Type: Storm Drainage
Awarded the contract by the City of Orlando, SanPik installed approximately 3,000ft of storm drainage ranging from 18″ up to 54″. SanPik also installed a large baffle box, approximately 2,000ft of 8″ sanitary sewer with manholes and a 2″ water main replacement.
Lake Davis to Lake Greenwood
Flewelling Avenue Stormwater Treatment System Project
- Type: Storm Drainage
This quick project, which was awarded to SanPik, Inc. by the City of Ocoee consisted of the installation of approximately 500’ of RCP pipe ranging from 15” to 54” diameter and 5 structures.
Flewelling Avenue Stormwater Treatment System Project
Cloud Branch Drainage Improvements Phase III
- Type: Storm Drainage
SanPik was awarded the contract by the City of Sanford for drainage improvements covering a large community near downtown Sanford from 10th Street to 20th Street. The project included over 7,000’ of RCP drainage pipe varying from 15” up to 72” diameter. Included in this project was also over 100 drainage structures and other various existing utility relocations.
Cloud Branch Drainage Improvements Phase III
Our Main Service Areas

Water Main

Lift Stations

Sewer
